N560LH Robinson Helicopter Company R44 II accident

NTSB WPR14CA270 · 2014-06-27 · Quincy, WA

Docket — crew, injuries and powerplant

Summary

The pilot reported that while drying cherries, he inadvertently let the main rotor blades strike a wind generator tower. The helicopter became uncontrollable, hit the ground hard, and came to rest in the orchard. The main rotor blades and airframe sustained substantial damage. The pilot reported no preimpact mechanical malfunctions or failures with the airframe or engine that would have precluded normal operation.

Full narrative

The pilot reported that while drying cherries, he inadvertently let the main rotor blades strike a wind generator tower. The helicopter became uncontrollable, hit the ground hard, and came to rest in the orchard. The main rotor blades and airframe sustained substantial damage. The pilot reported no preimpact mechanical malfunctions or failures with the airframe or engine that would have precluded normal operation.

Probable cause

The pilot's failure to maintain clearance from a wind generator tower while drying cherries, which resulted in a loss of aircraft control and subsequent hard landing. The National Transportation Safety Board determined the probable cause of this accident.

Circumstances

Event type
Accident
Highest injury
None
Weather conditions
Visual Meteorological Cond
Light condition
Day
Sky condition
NONE
Ceiling (ft)
0
Visibility (sm)
10
Wind direction
220
Wind speed (kt)
9
Temperature (F)
79
Distance from field
0.0

Aircraft

RegistrationMakeModelDamageFAR part
N560LH ROBINSON HELICOPTER COMPANY R44 II SUBS 091

Sequence of events

#OccurrencePhase
1 Maneuvering-low-alt flying Low altitude operation/event defining Climb
2 Maneuvering-low-alt flying Collision with terr/obj (non-CFIT) Climb

Findings

Finding
Personnel issues-Psychological-Attention/monitoring-Monitoring environment-Pilot cause
Personnel issues-Task performance-Use of equip/info-Aircraft control-Pilot cause
Environmental issues-Physical environment-Object/animal/substance-Pole-Effect on equipment factor